Home / Media / Three HPAL 40T35M gantry cranes landed smoothly

Three HPAL 40T35M gantry cranes landed smoothly

Time:2022年 02月 07日 Hits:6115次

On the morning of January 21, 2022, the ZHIXIAN II ship carrying three 40T/35M gantry cranes slowly departed from Nantong Rongsheng Terminal, and after completing a series of customs declaration and vessel procedures, sailed towards the destination port of the OBI Island in Indonesia. The three 40T/35M gantry cranes carried are mainly used for lifting cargo at the general cargo terminal of the acid leaching OBI project Phase II in Indonesia. This crane model has various functions and can lift various cargo, and can be used for the unloading bulk cargo ships and complex individual structures.

 

 

In order to ensure progress and save time in this shipment and enable the equipment to be put into use on the OBI project site earlier, the manufacturer considered for multiple processes and from different aspects. Finally, it was determined that the three gantry cranes would be lifted onto the ship as a whole. After the final assembly and debugging of the gantry cranes, a 1,600t gantry crane would be used to directly lift the cranes as a whole, with high efficiency and accurate positioning. This not only ensured that the gantry crane had a better completion status in domestic manufacturing, but also saved loading time, greatly reducing the construction workload before on-site delivery of the gantry cranes.

 

 

On February 1, 2022, the first day of the Chinese New Year, the ZHIXIAN II ship successfully docked at the general cargo terminal of the HPAL Project Phase II in Indonesia at 11:26 a.m. The unloading of the gantry cranes this time adopted the whole machine rolling method, which was carried out through the winch and wire rope pulley block for overall rolling unloading.

 

 

On the afternoon of February 2, 2022, HPL's on-site general manager Zhang Baodong, HPL's on-site executive deputy general manager Shi Wentang, and OBI Park Management Company's deputy general manager Hu Honggen inspected and supervised the site. After a series of sufficient preparations from all parties, the entire machines began to unload by rolling at 16:50, and the first gantry crane was smoothly rolled to the shore at 17:08. The overall work schedule was tight and the task was heavy. With the orderly and reasonable organization and arrangement of the manufacturer and the active cooperation of the on-site personnel, the unloading of the first equipment was successfully completed!

 

 

On February 3-4, 2022, the second and third gantry cranes were successfully unloaded, and the third gantry crane was successfully rolled onto the shore at 17:33 on February 4, marking the successful completion of the gantry crane landing. The landing of the HPAL Phase II bulk cargo gantry cranes was an important milestone in the construction of the terminal, marking the upcoming operation of the Phase II bulk cargo berth. The use of the HPAL Phase II bulk cargo berth will greatly enhance the material loading and unloading operation capacity of the HPAL terminal, provide reliable guarantee for material loading and unloading for HPL and HJF production and operation as well as project construction!

 

日韩亚洲激情在线观看| 尤物久久91欧美人禽亚洲| 日韩黄片大全免费在线看| 成人午夜在线视频观看| 青青操精品视频在线观看| 一级片二级片欧美日韩| 国产精品伦一区二区三区在线| 国产剧情欧美日韩中文在线| 国产一区欧美一区日韩一区| 日本加勒比系列在线播放| 成人精品欧美一级乱黄| 日韩精品免费一区二区三区| 亚洲熟妇av一区二区三区色堂| 少妇淫真视频一区二区| 日韩精品在线观看一区| 日韩综合国产欧美一区| 欧美激情视频一区二区三区| 成人午夜视频在线播放| av国产熟妇露脸在线观看| 黄色激情视频中文字幕| 91欧美日韩精品在线| 在线亚洲成人中文字幕高清| 欧美日韩三区在线观看| 亚洲专区一区中文字幕| 亚洲国产精品一区二区毛片| 亚洲性日韩精品一区二区| 欧美日韩久久精品一区二区| 国产又猛又大又长又粗| 美女黄片大全在线观看| 国产亚洲午夜高清国产拍精品| 国产精品视频一区麻豆专区| 日木乱偷人妻中文字幕在线| 大伊香蕉一区二区三区| 91精品国产综合久久精品| 亚洲精品偷拍一区二区三区| 免费在线播放不卡视频| 欧美一区二区三区99| 欧美日韩亚洲精品在线观看| 国产精品刮毛视频不卡| 国产精品免费精品一区二区| 午夜久久精品福利视频|